The project scope includes replacing the existing 1200A switchgear and distribution board with one (1) 3000A switchgear and two (2) sub-distribution electrical panels at the SamTrans South Base Maintenance Facility located in San Carlos. In addition, the scope entails installation of ten (10) new battery electric bus chargers and ten (10) new pedestal dispensers, modifications to PG&E’s transformer, and necessary wiring and connections.
The 3000A switchgear and 10 new battery electric bus chargers and dispensers will be provided by SamTrans. Anvil Power Inc (API), will be procuring a new 2000 AF distribution board (EBD), a new 1200A distribution board (MDPO-2), a new automatic transfer switch, and bus duct.